• Michael Chain

Remedial Building Services

Updated: Feb 11

Project update: Blacktown Project


Network are well underway with the remedial repairs to the project at Blacktown

Excavation and footings are complete

Core holes over underground car park complete

Reinforcement installed for new underground columns

Abseilers are underway with the inspection of external walls, gutters, rain water heads & down pipes.








4 views0 comments

Recent Posts

See All

Network the remedial builder has been engaged for the multi storey window leaks at Breakfast point strata block. The Network team were selected over other remedial professionals for the works. Once ag

Network the remedial builder have been engaged for the concrete cancer repairs to unit 24 located in Drummoyne NSW. The Network team have completed testing and inspection holes to confirm the deterior